CAPEX | Incentive-Supported Deployment | 150 kW
Coordinated end-to-end project delivery, including stakeholder alignment, design coordination, execution, and post-commissioning support.
Managed end-to-end project delivery, including stakeholder alignment, design coordination, execution, and post-commissioning support.
150 kW installed capacity | 210,000 kWh annual generation
Established a reference project, influencing renewable adoption across other institutions
Reduced electricity costs and Scope-2 emissions by 55%
Achieved 38% project IRR through optimized system sizing and government subsidy
High electricity consumption with planned future load expansion
Need to maximize rooftop solar capacity within regulatory and space constraints
Target to achieve 100% renewable electricity consumption
Fragmented rooftop infrastructure requiring maximum capacity within limited available space
• Coordinated design of a 150 kW grid-tied rooftop solar system based on current consumption and future demand
• Installed higher capacity to support long-term energy offset and campus expansion
•Implemented under government subsidy scheme to improve project viability
• Adopted ballasted mounting structure to meet school structural requirements
•Coordinated stakeholders across client, vendors, and consultants to ensure smooth installation and commissioning